Quick Answer: Florida still had no operating hyperscale data center as of early 2026. Proposals as large as 4 gigawatts now face SB 484, the state’s new data center law, and local pushback. The Public Service Commission rejected Duke Energy Florida’s first large-load tariff in November, while FPL and Tampa Electric have filed plans requiring data centers to pay their full cost of service.
Florida began 2026 with cheap land, growing utilities and developers claiming gigawatt-scale ambitions for artificial intelligence data centers. By late November, a new state law governed how the biggest power users connect to the grid, the state’s utility regulator had rejected the first tariff filed under it, and several of the largest campuses had been denied, paused or tied up in water permitting. Here is where things stand as of November 20, 2026.
What does Florida’s new data center law require?
Gov. Ron DeSantis signed CS/CS/SB 484 in Lakeland on May 7, 2026. It became Chapter 2026-65, Laws of Florida, and took effect July 1, 2026. The bill passed the Senate 31–6 and the House 92–16. The governor’s office says it bars utilities from passing data center costs to residential and small business customers.
The law defines a large-scale data center as a site with a projected monthly peak electric load of at least 50 megawatts (MW). The Florida Public Service Commission (PSC) must develop tariffs and service requirements that “reasonably ensure that each large load customer bears its own full cost of service.” Covered costs include connection, operations and maintenance, and incremental transmission and generation. Permitted tools include upfront contributions, demand charges, financial guarantees, minimum-use commitments and long-term contracts. The PSC must propose its implementing rule by March 1, 2027. Utilities then have 60 days after a final rule is adopted to file compliant tariffs.
How does SB 484 treat water, local control and foreign ownership?
Water permits averaging at least 100,000 gallons per day need a conservation plan and a hearing, and reclaimed water must be used where a feasible supply reaches the property. Major modifications are treated as new applications.
Local governments keep zoning authority, including the power to reject a data center. Development deals must be disclosed after a confidentiality period, and utilities may not serve data centers controlled by foreign countries of concern. OPPAGA, the Legislature’s research office, must commission an independent impact study due July 1, 2027.
Why did regulators reject Duke Energy Florida’s data center tariff?
Duke Energy Florida was the first investor-owned utility to file under the new law. Its proposal included a 20-year minimum contract term, minimum monthly bill provisions and mandatory early-termination fees. It did not include new rates designed specifically for large-load customers. Duke said it would file such rates in a future rate case after its current agreement expires at the end of 2027.
After an August hearing, Commissioner Mike La Rosa wrote that the petition appeared facially noncompliant. Florida Rising and consumer advocate Walt Trierweiler opposed it, and in early November the commission voted it down. Commissioners found that Duke’s proposed tariffs excluded some large-load customers who would otherwise meet the law’s definition. They also found Duke had not shown that its existing rate schedules plus contract protections would ensure each customer pays its full cost of service. Duke must refile. As of August it had no large-load data center customers, but it is expected to serve the proposed Fort Meade campus.
How are FPL and Tampa Electric handling large-load customers?
What does FPL’s large-load rate structure require?
Florida Power & Light’s large-load rate structure predates SB 484; the PSC approved it in a rate agreement on November 20, 2025, covering 2026 through 2029. In an early October compliance filing, FPL told regulators it already satisfies the law. Applicants must:
- fund an engineering study of feasibility and cost;
- pay 100% of the cost of new generation needed to serve it, through an Incremental Generation Charge;
- build, own and operate its own substation, and pay up front for new or upgraded facilities;
- accept a minimum bill covering reserved capacity, along with credit-based collateral;
- sign a contract of at least 20 years from the in-service date, with an exit fee for early termination.
In January, FPL President Scott Bores said large data centers had not yet arrived but that FPL expects them and will need new generation and storage. FPL has not published a pipeline megawatt figure. The PSC review is pending.
What did Tampa Electric propose?
Tampa Electric (TECO) filed its large-load proposal with the PSC on September 30, 2026. Customers of 50 MW or more would sign contracts of at least 20 years, post collateral of up to $2 million per megawatt of contracted demand depending on credit, give three years’ notice before leaving, and pay exit fees tied to remaining infrastructure costs.
The first class, LLCS-1, is capped at 1 gigawatt (GW) of combined demand. Projects beyond that cap would move to a second class with project-specific cost calculations. TECO’s filing anticipates 600 MW of energy storage, 600 MW of new generating capacity tied to modernizing its Big Bend Power Station, and new transmission. Review could run into early 2027, and no major data center proposal was under review in Hillsborough County as of October.
An August 24 PSC order froze TECO’s base rates until January 1, 2028, but explicitly excepts large-load tariffs filed under the data center law.
| Utility | Filing / status (2026) | Key terms |
|---|---|---|
| Duke Energy Florida | First SB 484 filing; hearing in August; rejected by PSC in early November; must refile | 20-year minimum term, minimum monthly bill, exit fees; no new large-load rates |
| Florida Power & Light | Compliance filing in early October; PSC review pending | 100% of new generation cost, customer-owned substation, minimum bill, collateral, 20-year term, exit fee |
| Tampa Electric | Filed September 30; review may extend into early 2027 | 50 MW threshold, 20-year term, collateral up to $2M/MW, 3-year notice, 1 GW cap on first class |
Which major Florida data center projects have been proposed?
In February 2026, WUSF reported that Florida did not yet have an operating hyperscale data center. These are the largest documented proposals.
Where does the Fort Meade hyperscale project stand?
The Stonebridge project in Fort Meade, in Polk County, covers about 1,300 acres of former phosphate mine land. Plans call for 4.4 million square feet of buildings and more than 1 GW of capacity at full build-out. Developers put the investment at $2.6 billion and project nearly 500 jobs by 2031. Polk County approved $140 million in tax incentives over 10 years. Fort Meade commissioners unanimously approved a developer agreement on April 14 despite heavy public opposition.
Water is the unresolved issue. The Southwest Florida Water Management District said the city cannot supply the site through existing infrastructure and that a new permit needs board approval. The developer cut projected use to 50,000 gallons per day with closed-loop cooling. In an April 17 letter, Commerce Secretary Alex Kelly opposed the project, saying water demand was underestimated and the operator undisclosed.
What happened to Project Tango in Palm Beach County?
PBA Holdings proposed Project Tango on a 202-acre site in western Palm Beach County, next to the Arden community. The nearly 3.6 million-square-foot plan projected 600 MW of demand, 12 times the SB 484 threshold, and 600 employees. The County Commission denied it 5–1 on July 15.
On September 24, commissioners voted 6–0 to pause new applications for data centers of 50 MW or more for up to one year. A 2016 approval for two 100,000-square-foot data center buildings on the site remains valid.
What other large projects are in the pipeline?
In DeSoto County, DCIP Group won a rezoning in March for a 34-acre former power plant site. It has described a campus that could grow to about 1,300 acres and draw up to 4,000 MW, powered mainly by on-site natural gas from the Florida Gas Transmission pipeline. A commissioner estimated $26 million a year in local taxes from the first facility. In St. Lucie County, the Sentinel Grove Technology Park was pitched at 1,218 acres, 1 GW, $13.5 billion, and 370 jobs, with about $114 million a year in county taxes and $63 million for schools. After the county planning board voted 4–2 against it, the developer paused the project. Other proposals include an 813-acre Deltona Corp. request in Citrus County.
In April, Okeechobee County ended Indian River State College’s 9–10 MW “Okee-One” project, which had received a $1.5 million state grant before the Commerce Department withdrew support.
| Project (county) | Power | Investment / jobs / taxes | Status (latest reported) |
|---|---|---|---|
| Stonebridge, Fort Meade (Polk) | 1 GW+ at full build | $2.6B; ~500 jobs by 2031; $140M county incentives | City approved April 14; water permit pending |
| Project Tango (Palm Beach) | 600 MW | 600 jobs | Denied 5–1 July 15; county moratorium Sept. 24 |
| DCIP Group (DeSoto) | Up to 4 GW, on-site gas | ~$26M/yr local taxes (first facility, estimate) | 34 acres rezoned March; more parcels pending |
| Sentinel Grove (St. Lucie) | 1 GW | $13.5B; 370 jobs; ~$177M/yr county + school taxes | Paused after 4–2 board vote against |
| Okee-One (Okeechobee) | 9–10 MW | $1.5M state grant | Ended by county vote April 23 |
How widespread is local opposition to data centers in Florida?
As of late June, E&E News counted at least 20 Florida counties and municipalities that had passed or discussed data center moratoria, some temporary and some permanent. Nassau County adopted a 12-month moratorium in June. Palm Beach County followed in September. Gubernatorial candidate Byron Donalds has proposed requiring large data centers to secure their own power and water.
What does this mean for Florida businesses and ratepayers?
Every tariff and the statute assume data centers, not existing customers, pay for new generation, and the Duke ruling shows the PSC will reject filings that leave that open. Terms are converging: 20-year contracts appear in all three utility frameworks, and TECO matches the statute’s 50 MW threshold. The rules are not final until the PSC’s 2027 rulemaking. Meanwhile water permits, zoning votes and moratoria, not power supply, have decided project fates so far.
Frequently Asked Questions
What counts as a large-scale data center in Florida?
Under SB 484, it is a site with a projected monthly peak electric load of at least 50 megawatts.
Will Florida households pay for data center power costs?
SB 484 requires tariffs that reasonably ensure each large-load customer bears its own full cost of service.
Does Florida have an operating hyperscale data center?
Not as of February 2026. Fort Meade’s project has city approval but needs a water permit.
Can Florida counties block data centers?
Yes. SB 484 keeps local zoning and land-use authority. Palm Beach County denied Project Tango and paused new applications of 50 MW or more for up to one year.
When will Florida’s data center utility rules be final?
The PSC must propose its rule by March 1, 2027. Utilities then have 60 days after a final rule to file compliant tariffs.
Sources and Further Reading
- Governor Ron DeSantis Signs Law to Protect Floridians from Subsidizing Data Centers – Executive Office of the Governor
- Florida’s New Data Center Framework – Florida State University College of Law
- Regulators reject Duke’s data center rate structure – WUSF / News Service of Florida
- New state law to protect consumers from data center costs faces first test – WUSF
- FPL tells regulators rate structure complies with data center law – WUSF
- Q&A with FPL President on expected data center growth and the company’s new customer protections – Florida Power & Light
- TECO proposes sweeping safeguards as Florida prepares for data center growth – Tampa Bay 28
- Order PSC-2026-0297-FOF-EI (Tampa Electric 2026 Bayside Agreement) – Florida Public Service Commission
- What to know about data centers in Florida: power, water, local control and the new law – News4JAX
- Proposals for massive data centers are popping up across Florida – WUSF
- Fort Meade moves forward with controversial $2.6B data center project – FOX 13
- Fort Meade AI data center project hits roadblock over new water rules – WUSF
- Florida’s commerce secretary comes out strongly against proposed AI data center – WUSF
- Palm Beach County rejects controversial Project Tango AI data center – WLRN
- Palm Beach County pauses large data centers; smaller Project Tango plan remains approved – CBS12
- Developers push massive data center complex in DeSoto County amid backlash – ABC7 Sarasota
- Massive data center, one of the world’s largest, proposed in rural Treasure Coast – AOL (syndicated)
- Scrapped data center in Okeechobee County mirrors rising opposition – WUSF
- Amid stark opposition, data center developers think twice about Florida – E&E News